Learning objectives
- Define levelized cost of energy and describe the project boundary to which a result applies.
- Derive the discounted lifetime-cost formula and identify the necessary time-value-of-money assumptions.
- Compute annual electricity output, capital recovery factor and a simplified annualized LCOE with consistent units.
- Calculate a degradation-aware solar PV LCOE, then compare a hypothetical wind project on identical financial assumptions.
- Quantify sensitivity to discount rate, capacity factor, curtailment and omitted project costs.
- Explain why LCOE is not the same as electricity price, project profitability or total power-system cost.
The levelized cost of energy (LCOE) converts the costs and useful electricity output of a generating project over its lifetime into a single average cost per unit of delivered electricity. It is usually expressed as USD/MWh or USD/kWh. It is valuable for comparing solar PV, wind, hydropower, bioenergy and other generating technologies when the analyst uses a consistent project boundary and financial basis. It is not a tariff, a guaranteed sale price, or an all-purpose ranking of the value of electricity at different hours [1, 2].
The basic intuition is simple: add all costs occurring across the project life after putting them on a common present-value basis; divide by the equivalently discounted electricity delivered across the same life. The details are consequential. Omitting financing-related construction costs, assuming an inflated capacity factor, mixing nominal and real discount rates, or counting electricity before curtailment can change the answer materially. This tutorial makes every assumption explicit, works through two illustrative technologies, and identifies the limitations before drawing investment conclusions.
1. What does LCOE actually measure?
LCOE answers a carefully scoped question: What constant value per unit of output would recover the included lifetime costs under the chosen discounting convention? A project-level LCOE generally summarizes capital expenditure (CAPEX), fixed and variable operation and maintenance (O&M), replacements, decommissioning where applicable, fuel when relevant, and the electricity supplied to the defined metering boundary. The exact basket differs among studies, so comparisons must inspect the methodology rather than rely on the headline number [1, 3].
For example, a low-cost solar plant might generate much of its output at the same sunny hours as many competing plants. Its project LCOE need not reflect the wholesale price it can actually earn in those hours, network congestion, or the flexible capacity the grid needs after sunset. The National Laboratory of the Rockies (formerly NREL) Annual Technology Baseline explicitly notes that LCOE alone does not establish the least-cost electricity-grid option [1].

Figure 1. Specify the system boundary before calculating LCOE: all included costs belong in the numerator, and the energy crossing the chosen delivery boundary belongs in the denominator.
A transparent study must document the plant size and whether it is AC or DC, commissioning date, currency and price year, expected service life, annual net export, the real or nominal discount rate, degradation and availability, and the inclusion of grid-connection, taxes, incentives and end-of-life costs.
2. Derive the discounted lifetime LCOE formula
Let C0 represent the project costs paid at year zero, Ct the net included cost in operating year t, Et the net delivered electricity in that year, r a discount rate consistent with the cost basis, and N the number of operating years. For a simplified project-cost model with no construction-period staging, define:
The levelized cost is their quotient:
All cost terms must share a consistent currency and price-year basis, such as constant-2026 USD with a real discount rate. If cash flows include projected inflation, use a nominal rate and calculate the corresponding nominal levelized price consistently. Real and nominal rates are linked through expected inflation:
Here i is inflation. The formula assumes the project outputs and costs have been appropriately allocated by year, including costs during construction when relevant. Discounting energy in this ratio does not suggest that electricity physically deteriorates because money has a time value; it is the mathematical operation needed to calculate a constant levelized price whose discounted receipts balance discounted costs [2]. Some detailed cash-flow models account explicitly for debt, taxes, depreciation, incentives and equity returns, and should not double count these by additionally inserting an incompatible project WACC [2, 3].
3. Capacity factor converts engineering performance into annual generation
A generator's rated capacity is power; annual electricity is energy. If P is the net rated AC capacity in MW and CF is the annual net capacity factor, a non-leap-year first estimate is:
For a hypothetical 10 MW AC solar PV plant with a first-year net capacity factor of 22 percent:
The capacity factor used here is the net delivered factor at the agreed meter, incorporating the modeled resource, losses and availability as appropriate. Do not subtract the same outage or curtailment twice. For wind, CF depends on the wind-speed distribution, turbine power curve, wake losses and electrical losses. For solar PV, it depends on solar resource, panel orientation, temperature, inverter clipping, shading, soiling and other operating assumptions. Hydro depends on hydrology, operating constraints and turbine characteristics [4].
4. Annualized LCOE and the capital recovery factor
A convenient screening model replaces the upfront investment by an equivalent uniform annual cost. For project life N and positive annual real discount rate r, the capital recovery factor (CRF) is:
With no degradation, no additional replacement/decommissioning cost, level annual net electricity, and uniform fixed O&M, a simplified pre-tax LCOE is:
F is annual fixed O&M in USD/year and V is annual variable O&M plus any fuel cost on a USD/MWh-delivered basis. For per-kW or per-MW cost inputs, carry the installed capacity consistently through both numerator and denominator. The more detailed fixed-charge-rate approach used in the Annual Technology Baseline can include financing/tax adjustments beyond this classroom CRF expression [3, 5].
The screening expression is not generally identical to a cash-flow LCOE when output degrades, costs escalate in real terms, replacements occur or incentives differ by year. In the following worked example we calculate both so that students can see the difference.
5. Worked example: 10 MW solar PV project with degradation
Consider an entirely illustrative grid-connected 10 MW AC solar PV project. These inputs are chosen for teaching arithmetic; they are not a current quotation, regional benchmark or feasibility estimate.
Input | Assumption
Upfront installed capital cost at year 0: USD 9.00 million
Plant life: 25 operating years
Real discount rate: 7 percent per year
First-year net AC capacity factor: 22 percent
First-year net export: 19,272 MWh
Annual fixed O&M, constant real: USD 150,000
Annual energy degradation: 0.5 percent of previous year's output
Variable O&M and fuel: Zero in this teaching example
Included tax, subsidy, storage and decommissioning items: None; explicitly outside this simplified boundary
Assume first-year energy E1 and fractional annual degradation d. Then year-t output is:
The discount factor for annual year-end cash flow t is:
For the 25 operating years, the present-value annuity factor for constant annual operating cost is:
The discounted degradation-weighted production multiplier is:
Calculate the present value of costs:
Calculate the discounted energy denominator:
Therefore:
The same value is approximately 0.04995 USD/kWh, or 4.995 US cents/kWh. Each energy and cost year is discounted using the same real rate, and degradation applies once per year after the first year. That is a reproducible project example, not a claim about the actual price of solar power in a particular market.
If we ignore degradation and apply the simpler annualized model, the CRF at 7 percent over 25 years is 0.0858105, giving:
This lower result is caused here by assuming output stays constant forever. The 2.09 USD/MWh difference is not a generic correction factor: it follows from the stated data and is sensitive to the project lifetime, discount rate and degradation assumption.

Figure 2. Discounted cost and electricity terms for the hypothetical solar project. Present-value energy is a financial denominator, not physical output lost by discounting.
6. Worked example: a wind project using the same method
Now analyze a hypothetical 10 MW AC onshore wind plant with the same 25-year life and 7 percent real discount rate. Assume year-zero capital cost of USD 13.0 million, fixed annual O&M of USD 400,000, first-year net CF of 36 percent, annual output degradation of 0.25 percent, and zero fuel and variable O&M. These are illustrative values, not market estimates.
Under these specific assumptions, wind has a slightly lower modeled LCOE than solar, even though its upfront cost is greater, because its net annual production is higher. This is not a universal technology ranking; changing wind resource, solar irradiance, connection cost or financing can reverse it. Avoid extrapolating either result to real regional projects without engineering yield assessments and current cost inputs [4, 6].

Figure 3. An apples-to-apples classroom comparison using the same financial lifetime and rate, with different project-specific costs, performance and degradation assumptions.
7. Sensitivity analysis: why one LCOE number is not enough
Discount rate and capacity factor often influence LCOE strongly, particularly for capital-intensive projects. Keep the solar example's capital cost, O&M, life and degradation unchanged while varying the real discount rate and year-one net capacity factor:
Real discount rate | CF 18 percent | CF 22 percent | CF 26 percent
4 percent: 48.38 USD/MWh | 39.59 USD/MWh | 33.50 USD/MWh
7 percent: 61.05 USD/MWh | 49.95 USD/MWh | 42.26 USD/MWh
10 percent: 75.11 USD/MWh | 61.46 USD/MWh | 52.00 USD/MWh
This sensitivity table changes two assumptions at once but holds the others fixed; it is not a forecast distribution or a confidence interval. A bankable estimate needs linked scenarios for capacity factor, capital investment, losses, degradation, replacement schedules, inflation, financing and regulatory rules. For example, improved tracking may increase annual production but also increase capital and maintenance costs. A technology choice should be made from the combined consequences, not the improved CF alone.

Figure 4. Under a common project boundary, low output and high financing costs both push the modelled cost per delivered MWh upward.
8. Curtailment, storage and the electricity-delivery boundary
If curtailment removes some otherwise exportable energy, the denominator must represent net electricity actually delivered. As a simple isolated scenario, hold annual cost and the PV generation profile of the solar example unchanged but assume an additional constant 8 percent curtailment of its modeled net export in every year. Then:
This case assumes no reduction in cost and no offsetting savings or revenue. In reality curtailment may vary by hour and year and correlate with the value of electricity, while system redesign may change both costs and exported energy. Count losses and curtailment once, using clear metering and scenario definitions.
For solar-plus-storage, simple PV-only LCOE is inadequate if storage changes capital costs, energy delivered, charging purchases and losses. Where suitable, calculate a consistently defined hybrid LCOE or levelized cost of storage (LCOS), distinguish electricity generated from electricity discharged, and assess the timing/value of delivered energy. Storage shifts energy but is not a primary energy source, and counting stored discharge as new generation inflates the denominator. The U.S. national laboratory's System Advisor Model treats LCOE and storage cost as distinct financial concepts [2, 7].
9. LCOE versus electricity price, NPV, IRR and system value
LCOE is a cost benchmark, not a prediction of market price. PPA price is a contract price subject to delivery schedule, escalation, credit and curtailment provisions. Net present value (NPV) includes priced revenues and expenditures and tests whether expected discounted project cash flows satisfy an investment benchmark. Internal rate of return (IRR) finds the rate that drives net present value of specified cash flows to zero, when a meaningful solution exists. System value considers which hours and locations electricity serves and the costs of reliability, balancing and networks.
The project NPV equation is:
Here Rt and Ct are properly timed cash inflows and outflows. If expected realized electricity prices are low during production hours, a project with a low LCOE may still have poor NPV. Conversely, high-value dispatchable generation can have a higher LCOE but deliver a more valuable service. The UK's 2025 electricity generation cost report explicitly identifies project LCOE as the cost of a generic generation plant, not a complete assessment of system value [8].
A common error is to rank wind, solar, gas and battery options solely by raw LCOE without matching their operational characteristics. Renewable generation at noon is not necessarily a substitute for dispatchable supply at 9 pm. A grid integration study should consider the hourly load and supply profile, network capacity, backup or flexibility requirements, reliability targets and market design.
10. Engineering applications and optimization choices
An LCOE model is useful wherever engineers can alter physical design and want to understand the economic effect. Examples include choosing PV tilt, tracker configuration and DC/AC ratio; selecting wind turbine hub height, rotor size and layout; comparing hydro turbine and head-loss alternatives; planning geothermal parasitic pumping; or evaluating bioenergy fuel-preparation requirements. The correct objective is not always minimum LCOE: a project may instead maximize NPV, meet a reliability or carbon constraint, or minimize total electricity cost across a portfolio.
A transparent design workflow is: establish the energy-service and metering boundary; model time-resolved net energy; assemble capital and operating cost estimates; specify a consistent financing and inflation basis; calculate year-by-year discounted costs and electricity; run sensitivity analysis; then compare LCOE with commercial revenue, grid constraints and alternative designs. The model's engineering assumptions should be traceable to data and the economic results should be checked for unit mistakes.
The simplified numeric examples here omit contingencies, taxes, insurance, land cost differences, debt structure, warranties, salvage and other items. This omission is intentional for teaching. It is not appropriate to call the classroom 49.95 USD/MWh solar estimate a bankable bid or current project price. For more detailed, traceable project-finance calculations, use a validated modeling framework such as SAM and independently check its input assumptions [2, 5].
11. LCOE practice problems with solutions
Problem A. Annual generation. A wind farm has 40 MW of net installed capacity and an annual net CF of 32 percent. Estimate its first-year output.
Problem B. Unit conversion. Convert 65 USD/MWh to USD/kWh and US cents/kWh.
Problem C. Capital recovery factor. Find the approximate CRF for a 20-year project at 8 percent per year.
Problem D. Simple annualized cost. Using Problem C, calculate the LCOE if installed capital is 6 million USD, annual fixed O&M is 110,000 USD, annual net export is 15,000 MWh, and variable costs are zero.
Problem E. Curtailment effect. A project has a calculated LCOE of 60 USD/MWh before curtailment. Assuming its costs are unchanged, what is the adjusted LCOE if 10 percent of energy is curtailed?
Problem F. Real and nominal discount rate. If the expected annual real rate is 6 percent and inflation is 3 percent, calculate the corresponding nominal rate.
Problem G. Critical interpretation. Two plants report 45 USD/MWh and 55 USD/MWh. Which is more profitable? Solution: The information is insufficient. Compare their site-specific prices, delivery timing, project boundaries, annual cash flows, financing, contractual risk and grid services. LCOE alone cannot determine profitability.
12. Summary and engineering checklist
The core relationship is lifetime discounted cost divided by lifetime discounted delivered energy. For the teaching examples, that produces approximately 49.95 USD/MWh for a 10 MW solar PV system with modeled degradation and 49.10 USD/MWh for a hypothetical wind project under different physical and cost assumptions. These are demonstrations of method rather than universal market values. Published studies from IRENA and national energy agencies report technology- and region-dependent empirical statistics using their own boundaries and cost years [6, 8].
When evaluating a reported LCOE, check the currency and price year, cost items, gross versus net output, discount rate, degradation, replacement and decommissioning treatment, project life, taxation/incentives and whether the reported number includes network and system costs. If any item is unknown, treat the headline LCOE as a starting point, not an investment decision.
Continue learning: Solar panel efficiency explained, Wind turbine power and energy calculations, Renewable energy grid integration, and Industrial energy and exergy analysis. These links connect resource assessment, physical conversion efficiency and systems thinking to economic performance.